Success Case - Steel
How Harumi Cut Setup Time by 75% in Hot Strip Mill Sequencing
The Challenge: Gaining Line Time Without Losing Orders

Overview
The customer is a global producer of stainless, electrical and specialty steel, with around 12,000 employees, 2.5 million tonnes of flat steel capacity in Brazil and Europe, and customers in more than 40 countries. The project focused on the company’s Hot Strip Mill operations in Brazil.
In a Hot Strip Mill (HSM), the order in which production orders are processed determines how many times the line has to change its configuration. Every changeover takes time that could otherwise be spent rolling.
For this company, Harumi turned the sequencing decision into a source of efficiency. We built an optimized schedule and compared it with the manual sequencing used as the baseline.
Sequencing only to minimize changeovers is not enough. The schedule also has to account for the orders themselves, the materials available, and their due dates. The goal was to find a better combination of these decisions while keeping the scheduled volume intact.
The Solution: Optimized Sequencing with Harumi
Harumi brought production orders, materials, and setup parameters into a single mathematical optimization model.
Under the same conditions as the manual baseline, the model:
defines a new processing order for the scheduled production orders;
organizes the transition from one order to the next to reduce configuration changes;
accounts for available materials and their due dates;
keeps every order that was scheduled in the baseline;
measures the impact of the sequence on the line and on inventory.
A New Sequence for the Same Demand
The optimized sequence scheduled every order included in the baseline. The difference showed up in the time needed to prepare the line: about 75% less setup time. By organizing the transitions between orders more effectively, the solution freed up time in the schedule without giving up any of the demand covered in the comparison.
The scheduled window was also about 7% shorter. This follows from the setup reduction: less time spent on configuration changes concentrates production into a tighter schedule.
Orders
All orders from the baseline scheduled
Setup
About 75% less setup time
Scheduled window
About 7% shorter
Material wait
About 12% less waiting time before the reheating furnace
Charging temperature
Potential average gain of about 176 °C in simulated scenarios
The results also reached inventory. In Harumi’s sequence, the time materials waited before entering the reheating furnace was about 12% shorter than in the baseline, roughly two hours less per material on average.
The comparison gives planners a clear view of the effect of each choice: keeping the order volume, reducing preparation time, and processing materials sooner. That combination is what turns sequencing into a tool for making better use of line capacity.
Potential Thermal Gains from Sequencing
Beyond setup and waiting time, the simulations identified an additional opportunity: making better use of the slabs’ heat before rolling.
By synchronizing steel shop production with HSM scheduling, the model can prioritize freshly produced slabs that still hold high temperatures. In the simulated scenarios, this synchronization showed an average potential gain of about 176 °C in slab charging temperature, compared with the daily average temperatures of the actual operation.
This points to potential for less reheating and, as a result, lower energy consumption. Beyond cutting setups and processing materials sooner, sequencing can also contribute to a more energy-efficient operation.
Manual Sequencing vs. Harumi
Before
With Harumi
Sequence built manually
Sequence defined by a mathematical optimization model
Frequent configuration changes on the line
About 75% less setup time
Longer scheduled window
Scheduled window about 7% shorter, with the same orders
Materials waiting longer for the furnace
About two hours less waiting per material, on average
Slab temperature not considered in the sequence
Potential to charge hotter slabs by synchronizing with the steel shop
Case Study Summary
Harumi turned Hot Strip Mill order sequencing into a lever for line capacity. With the same orders and the same conditions as the manual baseline, the optimized sequence cut setup time by about 75%, shortened the scheduled window by about 7%, and reduced material waiting time by about 12%.
The simulations also showed that synchronizing the HSM with steel shop production could raise slab charging temperatures by about 176 °C on average, pointing to lower reheating needs and energy use.
-75%
Reduction in setup time.
Every order from the manual baseline was still scheduled.
-7%
Shorter scheduled window.
Less time on changeovers concentrates production into a tighter schedule.
-12%
Less material waiting time.
About two hours less per material before the reheating furnace, on average.



