Success Case - Foundry

How Harumi Made Molding Planning More Predictable and Integrated with Melting

The Challenge: Planning Without Visibility into Production or Yard Capacity

Harumi Industry Image Case

Overview

Before Harumi, Molding followed the Melting schedule without a predefined sequence that accounted for production cycles, setups, processing times, production pace, and future staging area occupancy.

To decide which work order to run, the operator had to physically check the available materials and resources. In addition to taking time, this routine required walking around the facility and performing repeated checks, increasing the operational effort and fatigue over the course of the shift.

When inputs were unavailable or delays occurred, the operator moved on to the next work order. Without a forecast of when each load would be ready or how much space would be available, the melting sequence had to be changed every day.

The team spent approximately one hour per day reviewing the schedule. The lack of consolidated metrics also made it difficult to understand production capacity and efficiency losses. As a result, Production Planning and Control, supervisors, and operators worked primarily in a reactive manner.



The Solution Integrated Planning with Harumi


Harumi turns the Melting schedule into a detailed Molding plan, processed in approximately one minute.

The platform:

  • sequences work orders within melting groups;

  • sets planned start and finish times;

  • accounts for setups, changeovers, and processing times;

  • projects staging area occupancy;

  • calculates the time buffer between the completion of each work order and its melting time;

  • flags risks of delay, overload, and insufficient capacity;

  • compares different production configurations;

  • supports resequencing when the original plan is not feasible;

  • consolidates the information needed for decision-making, reducing reliance on repeated physical checks.



Simulation and Process Knowledge


The project also made it possible to structure metrics such as OEE, processing and setup times, resource utilization, idle time, takt time, and staging area capacity.

At Rollover, for example, the simulation determines the takt time and the appropriate number of positions or models produced in parallel. Each configuration is evaluated based on its effect on work order completion, resource utilization, and staging area occupancy.

This makes it possible to balance the pace of Molding with demand from Melting, avoiding both early production, which can overload the staging area, and late completion of loads.

Dimension

Dimensions & Metrics

Metrics

Delivery

Completed work orders and delay tracking across the planning horizon

Capacity

Resource utilization, available capacity, and shift requirements

Efficiency

OEE, idle time, and cycles produced per hour

Setup

Number and duration of changeovers

Staging area

Average and maximum occupancy, available positions, and peak time

Synchronization

Time buffer between work order completion and melting time

Production pace

Takt time and number of positions or models running in parallel

Planning

Processing time and plan-to-actual adherence


The output files complement the dashboard with information about work orders approaching their melting deadline and work orders outside the planning horizon. Together, this information helps identify bottlenecks, monitor resource use, and quickly assess whether the plan can meet demand. It also reduces the time spent searching for and manually consolidating information, allowing the operator to focus on executing and monitoring the process.


Support for Management Decisions


In one real case, the simulation showed that the available capacity would not be sufficient to meet demand. With this information, management identified in advance the need to add a production shift.

The project therefore goes beyond work order sequencing. It also supports decisions about capacity, machines, shifts, and staffing before a lack of resources disrupts the schedule.




From Reaction to Anticipation


Before

With Harumi

Decisions made during operations

Planning completed in advance

About one hour of manual review each day

Plan processed in approximately one minute

Operator physically checked availability

Consolidated information supports decision-making

Repeated walking and checks

Less operational effort required to review the schedule

Future staging area occupancy unknown

Occupancy projected across the planning horizon

Metrics not clearly structured

Efficiency, time, and capacity measured

Production pace based mainly on experience

Takt time and parallel operations evaluated through simulation

Bottlenecks identified after affecting operations

Risks flagged in advance

Resource needs identified during execution

Capacity, shifts, and staffing evaluated in advance

Information scattered across departments

Management dashboard provides an integrated view

Molding and Melting planned separately

Schedules synchronized

Case Study Summary

Harumi turned Molding sequencing into an operational and management planning tool. By simulating the production pace, resource capacity, work order times, and staging area occupancy, the platform increased predictability, integrated Molding and Melting, and created a quantitative basis for decisions about capacity, shifts, and priorities.

Centralizing the information also reduced reliance on repeated physical checks, lowering the operational effort required to review the schedule and freeing the operator to focus on higher-value activities. In one real case, this visibility made it possible to anticipate the need for an additional shift to meet demand.




-38%

Reduction in late jobs.

AFM significantly increased the number of orders delivered on time.

-11%

Reduction in total setup time.

In practice, this meant more output with the same resources, without additional investment.

-100%

Reduction in manual planning time.

No more spreadsheets.

"

Before Harumi, our planning routine took a lot of time and, even so, it was difficult to understand why production wasn’t progressing as expected. Today, with real visibility into capacity, setups, and bottlenecks, we’re able to plan with confidence, reduce rework, and ensure more predictable deliveries.”

Before Harumi, our planning routine took a lot of time and, even so, it was difficult to understand why production wasn’t progressing as expected. Today, with real visibility into capacity, setups, and bottlenecks, we’re able to plan with confidence, reduce rework, and ensure more predictable deliveries.”

Nélio Cordeiro
Planning and Production Control Coordinator

Nélio Cordeiro
Planning and Production Control Coordinator

Contact

Let's optimize your planning decisions

Talk to our experts about how AI, optimization models, and our platform can help you make better decisions across demand, supply chain, and production planning.

By submitting the form, you are agreeing to our Privacy Policy

Contact

Let's optimize your planning decisions

Talk to our experts about how AI, optimization models, and our platform can help you make better decisions across demand, supply chain, and production planning.

By submitting the form, you are agreeing to our Privacy Policy

Contact

Let's optimize your planning decisions

Talk to our experts about how AI, optimization models, and our platform can help you make better decisions across demand, supply chain, and production planning.

By submitting the form, you are agreeing to our Privacy Policy

Solutions

Company

Resources

Contact

Login